Pre-drilling

This method loosens the soil by means of boring a hole of sufficient diameter through the difficult soil layer into which receive the pile must be installed. Pre-drilling is usually carried out by auger drilling. Pre-drilling may also be required on sites where it is important to avoid noise and vibration. Mechanical augers have been used to bore uncased holes to receive piles which are installed in the hole and then driven a short distance to their required bearing level. This method would only be used where cast-in-situ piles are unsuitable because of ground or structural conditions.

A limitation of pre-drilling is that the bearing capacity of the pile may be reduced due to decompression. This aspect must be taken into consideration when the load carrying capacity of the pile is estimated.