In English only

Westpile Shell Pile

Elements of a Shell Pile

The West Shell piling system uses short cylindrical concrete shells, which are combined to form a continuous concrete shaft. After installation of the concrete shells, the concrete pile is provided with a cast-in-situ concrete core.

Pile sections are driven, using a crawler mounted pile driving rig and can be installed at a rake of up to 1:3 both towards and away from the machine. Specially constructed rigs allow Shell Piles to be driven in headroom conditions as low as 6 m.

Cylindrical precast shells are threaded onto a central steel mandrel and rest on a precast concrete driving shoe. The complete assembly is driven to a depth corresponding to the length of the mandrel, using a purpose-designed driving head and drop hammer. The driving head allows the full weight of the hammer to strike the mandrel and the pile shoe, while a cushioned blow is transmitted to the shells. The intensity of blows, delivered to the shells, can be adapted to variations in driving resistance by adjusting the drive head.

Schematic overview of a Westpile Shell Pile

When the first mandrel section has been driven into the ground, additional concrete shells are threaded onto a second extension mandrel, which is attached to the top of the bottom mandrel. Then, the driving operation is repeated. Additional mandrels and shells can be added until the required depth is reached.

Once driven to the required depth, the steel mandrels are withdrawn, leaving a fully cased hollow concrete pile shaft. A suitable reinforcement cage is installed at the center of the pile. Thereafter, the hollow core is filled with concrete to form the completed concrete Shell Pile.

Care must be taken when driving this type of pile through ground, containing large boulders or onto steeply sloping bedrock. In such conditions the pile shaft may be deflected, which causes bending of the shaft. Then, it may be difficulty to withdraw the mandrel and to place additional shells. If the shells are not properly jointed, a too large part of the pile load is transmitted to the in-situ concrete core, which has a comparatively small diameter and limited load capacity. Also, if the piles are driven in groups, ground heave may cause separation of the shells, unless precaution is taken, such as installing the piles in a predetermined order, or by using pre-boring.

Westpile Shell Pile rig

The use of short pile shells has the advantage that the excess length of a completed pile is never more than one shell length. It also enables the core to be concreted to an accurate level - usually a maximum of 0,3 m above cut-off level. As a result, trimming a Shell Pile to cut off level is a rapid, low-cost process, compared with the often hidden costs associated with trimming conventional precast piles. In general, the depth of core concrete to be removed, averages 0,15 m. Exposed reinforcement bars are subsequently connected to the pile cap or ground beam reinforcement.

Execution sequence of a Westpile Shell Pile

Execution of a Westpile Shell Pile
  1. The pile shells are threaded on a steel mandrel, the diameter of which is slightly smaller than the internal diameter of the shell elements. A steel band, acting as a sleeve, is installed at each shell joint. The internal face of each joint band is coated with mastic to prevent water penetration. Finally, a pile shoe is fitted to the lower end of the bottom shell.
  2. The whole assembly is then driven into the ground, extending the pile length by addition of steel mandrel sections and concrete shells, until the required depth is reached.
  3. Withdrawal of the mandrel leaves a stable, water tight, hollow concrete column, at the base of which is an integral pile shoe
  4. Steel reinforcement in the form of a prefabricated cage, is placed in the hollow core, which is then filled with concrete and compacted. This concrete core, together with the precast shells, forms the final solid load bearing pile. As the core is cast-in-situ, there is no risk of damage to the concrete strength, which in the case of ordinary driven piles may be affected by high driving stresses.
  5. Completed pile, trimmed to cut-off level



Copyright ©1998-2009 GRV AB Legal disclaimer