Topic: Piling
Subject: Piling through RC slab
 
Author: John 2005-03-09  
     
  I have a situation where there is an RC slab of a retaining wall where the bored pile is required to bore through. The base is located approximately 5m below top of ground level. Is this possible? OR do I have to excavate to the base and remove the base before bore piling?  
   

 

back.gif (57 bytes) Return to subject 'Piling'

 

Follow-ups:

» Paul Summers, 2005-03-10
» Johnyeun, 2005-03-17
» YH, 2005-11-10