Topic: Piling
Subject: peak particle velocity
 
Author: Marijana Bulatovic 2003-11-26  
     
  1.
Are you aware of any regulation (in your area) on peak particle velocity required to protect structural integrity of adjacent structures (e.g. watermains/sewers) during pile driving?
We are currently evaluating if our 5mm/s PPV requirement at the trunk sewers/watermains is reasonable. According to some sources,PPV of 50mm/s will ensure that no structural damage to surrounding structures will occur during piling?!
2.
Do you think it is much more expensive to do piling under 5mm/s than under 50mm/s restriction?

Thank you :-)
 
   

 

back.gif (57 bytes) Return to subject 'Piling'

 

Follow-ups:

» K. Rainer Massarsch, 2003-11-26
» DAvid Coley, 2003-12-11

Show all follow-ups