Author:
Marc Gallagher
|
2003-01-29 |
|
| |
|
|
| |
Greetings, Does anyone have experience driving pipe piles into decomposed rock for high capacities (specifically mica schist in NYC). The rock is 50 to 100+ blows per 6" penetration with a split spoon. Contractor is looking to get 150-200T design loads but is concerned with creep. Looking for actual load test experience if possible.... Thanks, Marc
|
|
| |
|
|
Return
to subject 'Piling'
|
Follow-ups:
|