Author:
Alok Bhowmick
|
2002-06-29 |
|
| |
|
|
| |
I am going to use the polymer slurry to stablise the bore of 1.5m diameter piles, for a major bridge project in India. Can any one give me the following informations regarding polymer slurry :
a) What are the benefits of using the polymer slurry as against the conventional 'Bentonite Slurry'. b) What 'precautiona' & 'checks' are necessary at site for ensuring correct and appropriate use of polymer slurry. c) Is there any reduction in skin frictional capacity of bored piles, if polymer slurry is used?
|
|
| |
|
|
Follow-up:
| |
Author:
nagarajan
|
2002-07-12 |
|
| |
|
|
| |
hi, to save cost and time polymer slurry is best for bored piles.it will enhance the production faster. i am using polymer(from KB)for bored piles,dwalls for six years without any big problems. advantage of using polymer: no desanding required. just airlifting for 3o mins. 20 kg of polymer can replace of 2000kg of bentonite(1:200). u can prepare slurry in big quantity in short period.say about 30 min to 1 hr.in bentonite u cannot do it easily
can u please tell me what type of polymer your are going to use?if u can mail me i can help u .
bye naga
|
|
| |
|
|