I need information about slope stabilization employing bored piles. Thank you
|
|
| |
|
|
Follow-up:
| |
Author:
Orfilos
|
2003-01-17 |
|
| |
|
|
| |
Use the Viggiani analysis (Napoli University) based on his 1981 paper. Deduce the FoS at existing conditions, calculate the force/m run that you require in order to enhnace the FoS to the levels you set and then use the Viggiani method implementing Broms ultimate lateral resistances and shear forces in order to calculate your piling schedule.
|
|
| |
|
|